Here's today's question:
An Agile team is working on a complex
ERP customization and deployment project.
The team cannot deploy a couple of
features because the recipient department
is NOT ready for the changeover.
Which Scrum role is responsible for
removing this impediment?
a) Product Owner
b) Development Team
c) Scrum Master
d) Business Analyst
Drop your answer below
Full explanation in comments tomorrow.