I’m hoping there’s one or two people in this group that have exceptional planning skills and would be willing to help.

Has anyone tracked or planned their direct labour build thoroughly?

For example:

Day 1-3: Clear topsoil & level site

Day 4: dig foundations.

Day 5: poured foundations,

Day 35-39: concrete block work to floor level

Day 40: lay all waste pies & ducting

Day 41: backfill gravel for subfloor

Etc. ?