Image 1 — First big job quoting? Old barn tear down
Image 2 — First big job quoting? Old barn tear down
Image 3 — First big job quoting? Old barn tear down
Image 4 — First big job quoting? Old barn tear down
Image 5 — First big job quoting? Old barn tear down
Image 6 — First big job quoting? Old barn tear down
Image 7 — First big job quoting? Old barn tear down
Image 8 — First big job quoting? Old barn tear down
Image 9 — First big job quoting? Old barn tear down
Image 10 — First big job quoting? Old barn tear down

First big job quoting? Old barn tear down

Hello all, Over here in Michigan and we are quoting out a roughly 3300 ft.² old school barn tear down and all the foundations coming out with it.
We’ve never quoted a job this size so just wondering if anybody has any experience in what they would quote for this.
The customer wants it clean flat ground afterward. We really wanna get the job. Just don’t know where our numbers should be. We’re expecting this should be about a weeks worth of work tearing out wood tearing up concrete
I’m posting some pictures here to help give a better idea, all help is appreciated thanks

Edit: just to add from comments, I appreciate all the insight!
We have 3 sets of hands, Deere 333G, backhoe and 2, 7x16 dump trailers with 4’ sides
Dumping and hauling the cement out is our biggest concern about cost of that. Haul out or drop some roll off dumpsters on site? ATM the resident hasn’t decided on bringing in fill dirt after or not

Those barrels will be cracked open to see what’s hiding in! lol