2 resolutions approved for sharon
"City council during Wednesday night's regular monthly meeting also passed two resolutions approving the final land development plans for the two future data centers to be built by Keel Infrastructure."
Moses Lake starting to build
This is a satellite comparison images. Structures previously on site are gone. Ground has been cleared. Construction started June 8. Now independently verifiable from satellite imagery. This isn’t a press release. It’s visible from orbit.
They're from the Copernicus Browser. They provide access to satellite systems that routinely capture images. The resolution is, at best, 10m/pixel, which explains why it's not the same as Google Maps (satellite view). Anyway, it's free to use, so verify it independently!
Sharon back on track
Mercer Node Development permitting update.
• Chapter 102 Individual NPDES Permit
• Current status: Technical Review
• Completeness Review: Completed
• Technical Review started: June 16, 2026
• Target completion: November 16, 2026
• Application status: Under Review
The application has successfully completed the completeness review and is now undergoing the Pennsylvania DEP's technical review, where environmental impacts and engineering compliance are being evaluated.
No final approval or denial has been issued at this time. A permitting decision is expected after the technical review is completed.
https://permit-license-status.pa.gov/permits/c38ac5b8-c1e9-4943-a2e0-973f20835099
panther creed permit update
Keel committed to submitting a noise control plan, erosion and sediment control barriers, acoustic barriers, and a series of technical reports to ensure compliance with the Nesquehoning ordinance. If they meet the deadlines estimated by their staff, these should be ready for approval on July 22. This affects the DEP permits—which are based on the necessary earthworks—and could be the reason for the delays.
https://nesquehoning.org/wp-content/uploads/2026/03/Data-Center-Ordinance-Mar26.pdf
Sharon update
https://permit-license-status.pa.gov/permits/c38ac5b8-c1e9-4943-a2e0-973f20835099
Permit 102 remains in "Action required" status, with the technical review yet to begin.2mo! If the DEP grants a public hearing (probable,the site is heavily contaminated from the old Westinghouse plant), it won´t be ready by October
Panther creek permit update
Technical target pushed to Oct. 29. Permit E1302226-001 — Chapter 105, Water Obstruction & Encroachment. Covers crossing Nesquehoning Creek with fiber optics and piping. New technical target: October 29. Roughly a 2-month push from the prior date.
2 indexes
Keel will be added in the russel 3000 & russel 2000
keel & amazon
AWS exec Alex Maheu posted about meeting Quebec’s Premier & Vice-Premier, confirming huge long-term commitment to invest in Quebec. Who already has energized, hydro-powered data center capacity ready in Quebec? Keel