When does widening a tolerance actually reduce total product cost?
Disclosure: I work in industrial product-cost consulting. This is a technical discussion, with no service or link.
A wider drawing tolerance may remove a machining or inspection step. But it can also shift cost into assembly, yield, field reliability or supplier variation. The drawing change alone is not evidence of a net saving.
For a proposed tolerance change, I would put four before-and-after checks on one decision sheet:
Functional boundary: Which fit, load, sealing or life requirement does the dimension protect? Check the full tolerance stack, not the part in isolation.
Process evidence: Compare measured distributions by process and supplier. A better Cp/Cpk after widening the specification does not mean the process itself improved.
Real cost movement: Which machining, tooling, inspection or scrap cost is actually avoidable? Which assembly, warranty or sorting risk could increase?
Release evidence: What test or production trial demonstrates that the new range still meets the functional requirement, including worst credible combinations?
This is a decision framework, not a claim that wider is always better. ASQ describes process capability as performance against specification limits; that distinction matters when the limits themselves change.
For engineers who have approved a tolerance change: which evidence most often overturned the apparent piece-price saving?