40' run from stage 1 to stage 2 11wc 26kW Generator 360,000btu 3.95gph lp
There's my question. I've measured and I have approximately 40 ft of underground PE dr11 that I'm going to have to run then of course the two risers. It's a 26 kW Generac generator. On propane. I've read the charts, and asked ai. 1 in is where it says I should be. But the propane company, suburban propane, is telling me I only need three quarters. Is this accurate? I know I'm supposed to have about 10 ft after stage 2 regulator. That's going to prove challenging but I'll figure it out.
This is an above ground tank, all work is / will be permitted.
I'm going to use tracer line in my trench. I still need the tape as well correct?
Direction please~~?~~