Concrete pad vs. Gravel foundation
Having a hard time deciding between the two for a 12x16 shed that I plan to diy. 12x16 is more than I could diy for concrete pad and it seems like every concrete company I get ahold of doesn’t seem too interested to do it. I’ve had quotes for $2500-$6000. Timeline is usually 4-6 months out but because it’s a small job they may be able to get out and do it between jobs but no promises, which I understand. But there is very little follow up after initial discussion. Is this normal? Should I keep looking around for more estimates?
I’m eager to get started. I’d prefer a concrete pad to build on top of, but at this point I’m considering doing a gravel pad just due to ease on getting started and cost. I guess my question is, how much is it worth it in time and money to wait on a concrete pad vs starting soon with a gravel pad?