A fun one from SH mock exam
A project manager is planning the next release for the software development team. The team has completed two releases to date, and the product backlog for the next release has been confirmed.
Which of the following tools should the project manager use to plan the duration for the next release?
A. Product roadmap
B. Resource calendar
C. Work breakdown structure (WBS)
D. Burndown chart
--------------------------------------------------
This one is fun because PMI Infinity disagreed with Study Hall's answer. I challenged PMI Infinity to think of scenarios where SH's answer could be correct, and I can't decide if it's response is "yeah, but you have to tweak the question really hard to make it fit"
What do you think?
Correct answer, SH rationale, and PMI Infinity rationales are posted in a comment below.