Hi,

It’s been about 1 month waiting for form board survey, a lot of rain, and city responses before I could get contractor to dig footing.

I was looking online to see if grass growing within building before pour is okay or not, and was getting conflicted answers.

I am hoping to get pouring in next 2 weeks-3weeks.

Do I need to remove the grass growing or once they start digging and laying tarp and pouring, all of it will die eventually?

Edit: Home is on a pie shaped cul de sac. Forms was set first to get a form board survey to make sure I was not encroaching over building lines. We did not want to dig footings yet in case we went over building lines.

Edit: link to foundation plan and detail

https://drive.google.com/file/d/1ordypVdjyiTxpg-\_uklA\_M7HwdOgFMbX/view?usp=sharing