Power comes back. The cooling plant doesn't.
Power comes back. The cooling plant doesn't.
A short voltage sag or transfer can last only a few hundred milliseconds. The electrical supply recovers. That does not mean the cooling system recovers with it.
What I keep seeing: A pump VFD trips and sits there waiting for a manual reset. The controller reboots slower than the drive. A network switch comes back after the plant controller. The run command disappears during restart. Devices come back "healthy," but in the wrong order.
Individually, every piece can be doing exactly what it was designed to do. The failure is the recovery sequence of the system, not a single bad component.
For critical cooling, "can the electrical system ride through?" is only half the question. The other half is: after the disturbance, what brings the plant back to a stable operating state, and how long does that actually take?
Ride-through on the UPS or ATS doesn't help much if the first pump that should start has no permissive, or the lead/lag logic is still booting.
Curious how others handle this in real plants: Do you rely on VFD auto-restart, or do you keep restart authority in the plant controller / BMS? How do you enforce start order after a brownout, and do you ever commission a short sag test (not just a full outage)?
What usually bites you: drive faults, network, or a lost run command?