▲ 69 r/WaterTreatment+1 crossposts

Biannual sludge tank maintenance

finished this morning, we tried to get in before it got hot. we replaced 15 missing diffusers, found 4 of them on the floor and the rest are staying in the bottom of the sump, tried to use a rake to fish them out. and take out all the rags , sometimes the diffusers will have rags (baby wipes) in them and you can poke it out with a screwdriver. (it’s not biannual it’s Biennial every two years ) if blowers turn off or air flow unbalanced between two tanks and one tank not getting air, it will go septic and smell horrible

u/Comfortable_Bus_3125 — 7 days ago
▲ 742 r/WaterTreatment+2 crossposts

Wastewater Dewatering Press start up SOP

waste activated sludge at 2% solid is sent to the dewatering press and dewatering even more to 14% so it can be hauled by a truck to the landfill

u/Comfortable_Bus_3125 — 8 days ago
▲ 22 r/WaterTreatment+1 crossposts

sludge tank drain , clean , & replace aerators

thickening process, waste activated sludge is stored in aerated tanks then sent to the gravity thickeners, mixed with polymer and dewatered to 2% then sent to another sludge holding tank for dewatering presses

u/Comfortable_Bus_3125 — 8 days ago

breeding 56,000lbs of Rotifers , Nematodes , Free-Swimming Ciliates, Stalked Ciliates ,and some water bears

6000scfm with 1 blower

u/Comfortable_Bus_3125 — 11 days ago
▲ 15 r/water

water reclamation Bio-Reactor filling/start up

2 million gallon basin with aerators on basin floor

u/Comfortable_Bus_3125 — 11 days ago
▲ 35 r/drinkingwater+1 crossposts

clarifier timelapse with water and without

made this video to show interns when all the clarifiers where full with water so they could see how it operates

u/Comfortable_Bus_3125 — 11 days ago