Worried I won’t get paid
Took a work order to relocate 3 APs, 2 of which needed new cable runs.
Ran the cable, got everything mounted, and 2 of the 3 APs came up fine.
The third wasn't working, and before I could finish troubleshooting, the office closed and I had to leave.
Buyer wants me back Monday to finish.
Problem is I already have another work order booked Monday.
When I told him that, he sounded upset.
I'm not trying to walk away from it. I'm willing to come back another day later in the week. But now I'm worried he'll try to hold back pay for the whole job over the one AP, even though the runs and relocations are done.
For those who've been here:
Can a buyer withhold pay for completed work over one unresolved device?
Should I wait to close out the work order completely?