Pune Metro: Past, Present and Future
Past:
2017
Operational : 0 Km
Under Construction : 33.1 Km
Line 1 - 17.4 Km
Line 2- 15.7 Km
Present:
2026
Operational : 33.1 Km
Under Construction : 77.713 Km
Line 3 - 23.33 Km opening by December 2026
Line 1A - 4.413 Km opening by December 2027
Line 2A - 1.12 Km opening by December 2028
Line 1B - 5.46 Km opening by December 2030
Line 2B - 11.63 Km opening by December 2030
Line 4 - 25.64 Km opening by December 2031
Line 4A - 6.12 Km opening by December 2031
Future:
2028
Operational : 61.963 Km
Under Construction : 176.05 Km
Line 1B - 5.46 Km
Line 2B - 11.63 Km
Line 4 - 25.64 Km
Line 4A - 6.12 Km
Line 4B - 11.35 Km
Line 4C - 5.57 Km
Line 5 - 47.295 Km
Lohegaon Airport Spur Line (2C) ~ 3 Km
Purandar Airport Extension of Line 4C ~ 20 Km
Purandar Airport Express line ~ 40 Km
This gentleman disciplined those who entered from the wrong side today
Context : I was in a taxi with 3 of my friends and we saw this near Dadar East TT circle. Due to a lot of traffic many people on scooty and bike tried to use the wrong side to merge onto the main road. The person in the video got frustrated because they weren't allowing him to cross. He aptly gave them a piece of his mind.
Everyone from Zomato riders to richkids on their superbikes all were forced to back off and use the normal left side. It was refreshing to see that some citizens still care about civic sense in this country.
Mumbai from the air looks spectacular
Took these a month ago during take off from CSMIA.
Edit: corrected CSMT to CSMIA.
Mumbai wrapped in monsoon magic
The clouds parted just enough to reveal a city wrapped in rain. From above, Mumbai wasn’t a maze of streets or a rush of people—it was a watercolor of silver skies, restless seas, and quiet dreams.