Simple situation but can have an extreme out come
Building permit issued for a house
Foundations, frame,.roof etc. build
Inspections completed during the work. No issues here
Now, almost half way through the build,
Building department says they missed a requirement from the planning department and the location needs an environmental study, and they bunch of other random checks.
Of course these aren't cheap, had I known that building in this location, I would have build say 20m further down.
Large enough property to do that.
Also the entrance way and well was approved by the municipality as a condition for the property to be severed in the first place.
What are some options I have?